My oversight. I saw EIS and went straight to NEPA, thinking of US territories. I understand my error, thanks for all the corrections. Comment still valid minus NEPA reference...

Kate

Sent from my iPhone

> On Jul 2, 2015, at 4:09 PM, Kate Winters <katelwinters at gmail.com> wrote:
> 
> Where is the Site Selection Analysis?! Their document states that George Town Harbor is the only site assessed in the document...that is not proper NEPA analysis. Alternative sites should have been assessed and either dismissed or assessed further in this EIS?...not just alternative berthing designs. Even if people just toss a comment out on that missing information, it would help hold them accountable to properly assess the project per NEPA requirements.
> 